Regulations concerning the Performance of Work

  1. Part 1: Introductory provisions

    Chapter 1. Introductory provisions

  2. Part 2: Requirements for work involving chemical and biological risk factors

    Chapter 2. Substance index

    Chapter 3. Work where chemicals may be a risk to the health and safety of employees

    Chapter 4. Work with asbestos

    Chapter 5. Hot work

    Chapter 6. Work in surroundings that may entail exposure to biological agents

    Chapter 7. Work where there is a risk of reproductive harm

    Chapter 8. Work at wastewater treatment plants

    Chapter 9. Work with cytostatics

  3. Part 3: Requirements for work under exposure to physical risk factors

    Chapter 10. Requirements for the use of work equipment

    Chapter 11. Facilitating the use of work equipment

    Chapter 12. Inspection and maintenance of work equipment and plant

    Chapter 13. Work equipment subject to a requirement for inspection by a competent enterprise

    Chapter 14. Work that can entail exposure to noise or mechanical vibrations

    Chapter 15. Ionising radiation

    Chapter 16. Artificial optical radiation

    Chapter 16 A. Electromagnetic field

    Chapter 17. Work at height

    The employer shall ensure training for employees who will perform erection, removal, alteration and inspection of system scaffolds where the scaffold top deck height is from two metres and erected as standard and in accordance with the supplier's erection instructions.
    The training requirement also applies to the erection, removal, alteration and inspection of rolling scaffolds from two metres.
    The training shall take into account any elements of risk associated with the work and shall pay particular attention to:
    1. a.
      understanding the instructions for the erection, removal or alteration of the type of scaffolding in question,
    2. b.
      safety during the erection, removal or alteration of the type of scaffolding in question,
    3. c.
      measures to reduce the risk of falling for persons and objects,
    4. d.
      assessment of the condition of the scaffolding material to remove any unsafe scaffolding material, e.g. rot, corrosion and cracks,
    5. e.
      safety measures in the case of any changes in weather that may have a negative impact on the safety of the type of scaffolding in question,
    6. f.
      permitted loads,
    7. g.
      inspection of scaffolding and
    8. h.
      all other risks which may arise during the said erection, removal or alteration.
    Before an employee is assigned independent work involving erection, removal, alteration and inspection, the employer shall ensure that the employee has had 7.5 hours of theoretical training and 7.5 hours of practical training under the supervision and guidance of a qualified person. The employer shall also ensure that the employee receives training in the use of relevant safety equipment to protect against falls during the erection, removal and alteration of scaffolding constructions, including the use of personal protective equipment (fall arrest equipment).
    An employee who has completed such training according to this provision is considered a qualified person for scaffolding with a top scaffold deck height of up to five metres.
    Documentation shall be issued confirming that such practical and theoretical training has been given in accordance with this provision. The safety representative and the Norwegian Labour Inspection Authority shall have access to the documentation of the practical and theoretical training.

    Scaffolding that is not designed to stand freely or be suspended, shall be anchored by fastening or tying the scaffold to a rigid structure or the ground. Scaffolds shall have sufficient anchor points to secure them against overturning or breaking away.
    The fastening devices for the anchor ties shall be suitable for the material of which the supporting structure is made.
    The anchor ties shall be dimensioned according to expected wind forces at the site, both transverse and longitudinal. If anchoring devices have not been described in the assembly instructions, they shall be calculated. The calculations shall be documented together with documentation confirming that the construction to which the scaffolding is anchored, can withstand the total expected load.
    The anchor ties shall be fastened to the posts or the frames as close to tying points with the horizontal bearers as possible.
    The anchoring devices shall be able to absorb both tensile forces and compression.
    A row of anchoring devices shall normally be installed at the level of the uppermost runners.
    Anchoring devices shall be tested by applying a load that is 20% higher than the load for which they are designed.

    Chapter 18. Work with lifting equipment

    Chapter 19. Work with mobile work equipment

    Chapter 20. High-pressure jetting

    Chapter 21. Excavation work

    Chapter 22. Safety signage, signalling and communication

  4. Part 4: Requirements relating to other work that involves risk

    Chapter 23. Risk assessments, training and information in connection with manual work

    Chapter 23A Work that may entail a risk of exposure to violence and threats of violence.

    Chapter 24. Work on operations control and safety monitoring

    Chapter 25. Requirements for inspection, marking and filling of compressed air cylinders for diving and respiratory protection equipment

    Chapter 26. Health and safety during work under water or under increased ambient pressure

    Chapter 27. Rock work

    Chapter 28. Work in connection with carbon dioxide extinguishing systems

    Chapter 29. Work in or on tanks, pipelines, rooms etc. where flammable products or hazardous substances could be present

    Chapter 30. Risk of avalanches in occupancy areas and work areas

  5. Part 5: Register of exposed employees

    Chapter 31. Register of exposed employees

  6. Part 6: Final provisions

    Chapter 32. Final provisions