Section 14: Coordination

Coordination during the project preparation phase includes:

a) coordinating the project preparation in order to safeguard considerations regarding safety, health and working environment

b) ensuring that there is a plan for safety, health and working environment.

Coordination during the execution phase includes:

a) following up risk factors in the client’s plan for safety, health and working environment

b) following up the preparation of schedules to ensure that sufficient time is set aside for execution of the various work operations

c) following up compliance by employers and one-man enterprises with the plan for safety, health and working environment

d) coordinating work by employers and one-man enterprises whereby they may affect each other with regard to safety, health and working environment, including cooperation between employers and one-man enterprises

e) ensuring that employers follow up compliance with the requirements of section 9

f ) ensuring that lists are kept of persons employed at the construction site, see section 15.